The Buck Jenkins Service Center maintains 14 substations, 1,848 miles of line and serves 25,952 members. In the Oakland area, we will be replacing 125 poles. In the West Bowling Green area, we are upgrading 6,000 feet of line to carry the increased load between Glen Lily Road and the Natcher Parkway. We are going to build 3,000 feet of new line in the South Industrial Park to distribute the load more evenly in that area. We will be installing new underground primary in Baily's Farm subdivision on Three Springs Road. |
Gerald Smith District Manager Buck Jenkins Service Center |